Hi Malka,
I am not sure if you need Quota Arrangements. If you only want to use your second alternative BOM, you should only have active the production version for your second alternative BOM. Go to C223 and block the production version that is using the first BOM.
Be sure that your material in the MRP4 view of the material master has Selection Method = 3.
Thanks and Regards,
Mariano