Hi SAP experts,
I have a MTO scenario,
Order quantity: 10
Available Stock quantity : 0
when i save the sale order i get confirmed quantity as 0.
whereas a planned order is also created in background for some date.
My requirement is to get this planned date from planned order as the promise date in sale order. (i.e. quantity should be confirmed on this date).
I checked the controls settings for availability check and is configured with
Planned order : Marked as A (i.e. consider firmed planned order only).
Please let me know how can i get the confirmed date from planned order.
Regards,
Birendra