Please kindly assist me:

$
0
0

Hi PP experts ,

 

 

      Please kindly assist me ,

      Issue is : when i execute MRP(md02) for create re-planned orders after that when i go through CO41 for changing planned orders to prod orders,

           that time i i was not able to find required planned orders , what i have done with MRP execution .

 

 

           Example : when we fulfill sales order with required quantity as per client requirement . In that i have to go through 5 process according to my                   plant process with respective of  sap process for data key in .

 

              client required 100 pcs.

             process 1: out put 100 pcs data key in

             process  2: out put 100 pcs data key in

             process 3: ou put 100 pcs data key in

             process 4: out put 80 pcs and rejection(scrap) 20 pcs

             process 5: out put 75 pcs and rejection (scrap) 25 pcs .

 

        above situation i wanted to do replanned for rejection material for process 4 and process 5 .so with MD02 i run MRP

         after i will go through CO41 for conversion orders ,here only i will get big problem , i mean i was not able to find as per my

        required orders process 4 and process 5. But i found process 1, process 2, process 3  which i don't required .

        

 

  Please i kindly request you all experts , please help me to find the solution

 

 

 

Thank You .