Thank you for your replay.
The calculation key "2" is defaul but when I enter the control key PM03 the system shows me the following message:
Calculation of labor made in service package --> calculation key replaced
Message no. IW197
Diagnosis
You want the work to be calculated based on its duration, although a service package is assigned to the operation.
System Response
The system does not allow for the work to be calculated based on its duration for an internally-processed operation with a service package because in this case, the total work for the service package is displayed in the operation.
Procedure
Choose another calculation key.
And after that message the calculation key change to "0 maintain manually".
Regards,
Yolima