Hi,
I am sharing the MD04 screens for subsequents level material:
7111-296s is HALB material whose BOM contains another HALB material 7111-423.7111-423 contains a raw material 7176-191.
Here for level 1 and level 2 materials (7111-296s/080 and 7111-423) planned orders are getting generated weekly but for 3rd level material(7176-191) only one schedule line got generated.Why??
For example take april month requirements..
The lot size for each material in material master is WB that is weekly lot size..There is not any minimum or maximum lot size maintained for any material.
Please suggest.
Regards,
Blessedgirl