Hi Mahesh,
Go to Costing view 1 in material master and set "DO NOT COST" check box. when you execute cost estimate, system will ignore these materials.
Thanks,
Rau
Hi Mahesh,
Go to Costing view 1 in material master and set "DO NOT COST" check box. when you execute cost estimate, system will ignore these materials.
Thanks,
Rau